Abirami Builders piling works at Cuddalore
Back to Projects

Abirami Builders

Cuddalore

375 nos. of 600mm dia piles at 20m depth, in progress at Cuddalore.

Project Overview

A live package for Abirami Builders at Cuddalore covering 375 bored cast in-situ piles of 600mm diameter to a depth of 20 metres.

Rigs, tripods and slurry pumps were mobilised from our Chennai yard within days of award, a capability supported by our fleet of 10 tractor mounted hydraulic rigs.

Load testing equipment capable of testing up to 500 MT is available in-house for the confirmatory pile tests on this site.

Scope of Work

  • Setting out and verification of pile positions against the structural grid at Cuddalore, jointly signed off with the client's site engineer.
  • Boring / driving of 375 piles at 600 mm diameter to a founding depth of 20 m using the bored cast in-situ pile (dmc method).
  • Fabrication, lowering and centring of reinforcement cages with cover blocks to the specified concrete cover.
  • Continuous tremie concreting of every pile with cube sampling and pour records maintained per pile.
  • Chipping back to cut-off level, disposal of muck and handover of the as-built pile schedule.

Machinery & Plant Deployed

  • Tractor mounted rotary DMC rigs with mud pumps and circulation tanks
  • Bentonite mixing and desanding plant with specific gravity check kit
  • Weighted chisels for penetrating hard laterite and boulder strata
  • Reinforcement cage fabrication yard with bar bending and cutting machines
  • Tremie pipe assembly with hopper for continuous concrete placement
  • Transit mixers with on-site slump and cube testing

Execution Timeline

  1. Mobilisation

    Rigs, cages, casings and site establishment moved to Cuddalore, with access roads and working platform levelled for rig movement.

  2. Trial pile & test bore

    A trial pile was executed and observed against the borelog to confirm strata, penetration rate and concrete consumption before the production schedule opened.

  3. Production piling

    375 piles executed in a planned sequence to keep rigs clear of freshly cast piles, holding the In progress programme.

  4. Testing & handover

    Load and integrity testing on the agreed sample of piles, followed by trimming to cut-off level and handover of records to the main contractor.

Load Testing & Quality Results

Initial load testTest pile loaded in increments to 2.5 times the design working load as per IS 2911 Part 4, with each increment held until the settlement rate stabilised. Safe working load confirmed for the 600 mm pile section.
Routine load testWorking piles from the production schedule tested to 1.5 times design load. Settlement at test load and residual settlement after unloading remained within the permissible limits laid down in the code.
Pile integrity testLow-strain integrity testing carried out on sample piles; reflectograms showed continuous shafts with no necking or discontinuity down to the founding level.
Concrete cube testingCubes cast from every pour and tested at 7 and 28 days, with all results meeting or exceeding the specified grade.

Site Gallery

Bored Cast In-Situ Pile (DMC Method) in progress at Abirami Builders, Cuddalore
Bored Cast In-Situ Pile (DMC Method) in progress on site at Cuddalore.
Reinforcement cage lowering for piles at Cuddalore
Reinforcement cage lowered and centred before tremie concreting.
Completed pile heads awaiting trimming at Cuddalore
Completed pile heads awaiting trimming back to cut-off level.

Technical terms used above are explained in our piling glossary.

Scope Highlights

  • Rapid mobilisation from the Chennai equipment yard
  • In-house load testing capability up to 500 MT
  • Reinforcement fabricated and lowered under engineer supervision

Project Details

Client
Abirami Builders
Location
Cuddalore
Status
Running
Technique
Bored Cast In-Situ Pile (DMC Method)
No. of Piles
375 piles
Pile Diameter
600 mm
Depth
20 m
Duration
In progress
Enquire About Similar Work